Toby Keith Expressway Work Begins in Newcastle, With New River Bridges Opening From Late 2027

On Thursday, Oct. 22, a crowd gathered at 275 Snow Drive in Newcastle, an industrial site that now serves as the operating base for the new I-44 interchange. Officials from the Oklahoma Turnpike Authority and the Oklahoma Department of Transportation took turns with ceremonial shovels alongside Gov. Kevin Stitt, U.S. Sen. James Lankford, Newcastle Mayor Karl Nail and members of the Newcastle Chamber of Commerce. The Newcastle Pacer's photo coverage also shows Toby Keith's son, Stelen Covel, and Toby Keith Foundation director Juliet Nees-Bright in the group.

Manor Lake Hills sits off Highway 9 West, just west of Riverwind. From there, the Toby Keith Expressway will show up in two stages. First comes about a year and a half of work on the stretch of I-44 through Newcastle. After that, a new South Canadian River crossing opens between Portland and Pennsylvania avenues, with a direct line into north Norman.

Where the interchange work sits

The interchange that broke ground in October ties I-44, US-62 and SH-37 to the future expressway, according to News 9. That junction becomes the western end of the planned 28-mile route, which will eventually reach I-35, I-40 and the Kickapoo Turnpike.

The first phase has a price tag. In July 2026 the turnpike authority awarded a $75.4 million contract for new bridges and ramps connecting I-44, NW 24th Street and SH-37. The contract also covers service roads and work on the I-44 mainline. The finished interchange will stand four levels high, and KFOR reported that crews will also build frontage roads and new ramps at NW 24th.

A later phase reaches further along I-44. The Pacer's July report describes phase two as a rebuild of about two miles of I-44 between the Canadian River and NW 24th Street, along with a rebuilt NW 36th Street overpass. If your errands or commute run up I-44 out of Newcastle toward the city, that two-mile stretch is the one to watch.

How traffic keeps moving in the meantime

The rules for the work zone are already set. According to the same Pacer report, daytime I-44 traffic stays open with at least one lane in each direction, and OTA will announce intermittent nighttime closures ahead of time. KFOR reported that OTA hopes to keep I-44 open during peak periods and expects the interchange buildout to take about a year and a half.

A year and a half from an October 2026 groundbreaking runs into spring 2028, and that matches OTA's own target. At an OTA board meeting covered by the Norman Transcript, executive director Joe Echelle said the authority is aiming to open the I-44 interchange to traffic at the end of 2027 or early 2028, with at least one lane open in each direction by the end of 2027. He added that the timeline will firm up once the remaining projects are awarded and crews get through the winter weather.

In practice, I-44 through Newcastle will be a work zone through all of 2027. Night closures will come with advance notice from OTA, so checking those announcements before a late drive is the habit to build.

The bridges going up between Portland and Pennsylvania

For anyone on the Highway 9 corridor, the larger change is the river crossing. OTA is building a pair of bridges over the South Canadian River between Portland and Pennsylvania avenues. Construction began March 9, 2026, on a $97 million project, and the agency calls it the first major bridge component of the I-44-to-I-35 corridor, according to OTA's April 2026 update. At the October groundbreaking, KFOR reported the bridges were about 40% complete.

That same April update includes the figure that matters most on this side of the river. OTA projects the new crossing will cut the drive from the I-44/SH-37 area in Newcastle to downtown Norman from 16 miles to 12. On the Norman side, the expressway reaches I-35 near Indian Hills Road. OTA lists coordinated improvements at that I-35 connection and near 36th Avenue NW.

The bridges also open in stages. News 9 reported in October that OTA expects one side of the expressway to carry two-way traffic in late 2027 or early 2028, with the other side opening six to eight months later. KFOR put the first bridge opening to eastbound and westbound traffic in early 2028.

The calendar, from groundbreaking to full corridor

Date What happens Source
March 9, 2026 South Canadian River bridge construction begins OTA, April 2026
July 2026 $75.4 million Newcastle interchange contract awarded OTA, July 2026
Oct. 22, 2026 Interchange groundbreaking at 275 Snow Drive Newcastle Pacer
Jan. 5, 2027 Systemwide PIKEPASS rate adjustment takes effect Norman Transcript
End of 2027 Target for at least one lane each direction at the I-44 interchange Norman Transcript
Late 2027 or early 2028 One side of the expressway opens to two-way traffic News 9
Six to eight months later Second side opens News 9
2033 Full 28-mile corridor estimated complete News 9, September 2026

Echelle told the Norman Transcript that eight Toby Keith Expressway projects between I-44 and I-35 are under construction or about to start, at a little over $300 million in combined construction costs.

What the drive will cost

The new interchange on I-44 won't be tolled. OTA's November 2025 planning release says only the new East-West Connector, now the Toby Keith Expressway, carries tolls.

Rates are also going up across the system. Starting Jan. 5, 2027, the average PIKEPASS rate for passenger vehicles rises from 7.4 cents to 8 cents per mile. The Norman Transcript reported the change as the second in a series tied to the ACCESS Oklahoma bond program, after an increase in 2025.

Why the road carries Toby Keith's name

Until this year, the route was known as the East-West Connector, part of the ACCESS Oklahoma turnpike plan. The Legislature adopted HCR 1019 to honor Keith's Oklahoma roots, patriotism and service. The House approved it Feb. 25, 2026, and the Senate followed on Feb. 26, according to the Oklahoma House. KOSU reported on March 4 that the OTA board had approved the name that week. KOSU also reported that Keith first opposed the turnpike because it displaced friends and family, and that he reportedly changed his mind before his death.

At the groundbreaking, Echelle described the project's reach. "It's going to change how this area connects to the rest of the state and to the Oklahoma City area, and how the rest of the state can connect to this area," he told KFOR. Mayor Nail called "an opportunity to have another connection" incredible for Newcastle.

A separate OTA project, the South Extension, would run from the Toby Keith Expressway south to Highway 9 in Norman. OTA's June 2026 progress report puts that road on its own schedule, with one segment opening by 2032 and the rest by 2034. For drivers along Highway 9 West, the projects that change things before then are the ones in this post: the interchange work on I-44 through 2027, and the river bridges opening in stages starting in late 2027 or early 2028.

A new river crossing changes how Manor Lake Hills connects to Norman and the rest of the metro, the same way the Riverwind corridor already shapes the neighborhood's weekends. If you'd like to know how the new expressway figures into the value of your Manor Lake Hills home, Your OKLA Home can walk you through it. Get Your Free Home Valuation and we'll talk about what's changing in your corner of the county.

Work With Alaina

Alaina will provide services that entail integrity, high communication levels, & a drive that will ensure quality work through your next Real Estate venture! Contact her today!

Follow Me on Instagram